In cold weather slide the panels tight against the eave flashing and in warm weather allow a gap for expansion.
Standing seam metal roof installation instructions.
I prefer a hatchet but in some.
Standing seam metal roof installation process.
Use endwall flashing to locate correct position of zee closures.
From underlayment venting layout.
Fasten panel side with number ten pancake head screws and the top of the panel with three number fourteen mill points.
We cover all the basics of metal roof installation.
Install endwall flashing onto zee closures by riveting flashing to top flange of zees at 18 inches on center onto top flange of zee.
When used extended drip edge should be installed first along the drip edge of the roof.
Install zee closures onto panels at both sides.
Installation of a standing seam metal roof involves joining vertical interlocking panels from the top of the roof ridge to the roof s eave edge.
The lower end of each panel is then trimmed and the hem pre bent before installation see pg 9.
Step by step instruction on how to install a standing seam metal roof.
The area where each panel joins the next is raised above the roof s flat surface.
Place the first panel with overlap leg along the alignment line.
Basic preparation for the job the most important thing about installing standing seam is to measure the roof.
Pancake screws are applied to the nail strip of the standing seam panels.
Apply row of tube sealant along back face of zee closure adjacent to panel legs.